Bridge Design consultancy for checking the suitability of the existing well foundation for 25 T Axle loading- Two tracks for Kalpi bridge ( clear span 76.2 m, 10 spans – steel Through type girder- 2 tracks)

Kalpi Rail Bridge was completed& inaugurated on 1888 by Indian Railway. The total length is near about 820 Meter across Yamuna River. The bridge was 125 years old & made by bricks masonry. To check whether the existing bridge strength is sufficient for execution of second B.G. line.

Services provided:

  • Site inspection of the bridge and review of the old drawings available with Jhansi Railway Division.
  • Make design calculations for the bridge with latest loading and as per the existing Bridge and IS codes.
  • Get the calculations proof checked at IIT Chennai.
  • Post that a complete due diligence report to be provided to the client for their decision.